Completion Date: November, 14 2019
Location: Pennsylvania
Client: Rice Energy
PGI was engaged by Rice Energy to construct 17.2 miles of 30″ pipe, 2.1 miles of 16″ steel and 18″ HDPE colocated. The project consisted of limited, narrow right of way with maximum work space of 75 feet on the 30″ diameter line. The region was also very mountainous, which made the project extra challenging. Additionally, there were to HDDs on the project one of which required a redesign with extreme logistical challenges on the exit side of the drill. Project time frame was July 2014 through November 2014.
Pipeline and facility construction projects delivered for our clients throughout the US.
Learn MoreGet your project started by contacting our team for a project evaluation and quote.
Contact Us